High Court told of satisfaction with Priory Hall works

WORKS TO address serious fire safety risk at the Priory Hall apartment complex are under way and the fire authorities are broadly…

WORKS TO address serious fire safety risk at the Priory Hall apartment complex are under way and the fire authorities are broadly satisfied with the progress made to date, the High Court has been told.

However, lawyers for some residents expressed concern about other possible defects in the 187- apartment complex at Donaghmede. They have sought building reports from Dublin City Council, which earlier this month secured orders requiring evacuation of the complex and remedial works to be completed by the end of November.

The court heard yesterday that some of the 240 residents who were moved from the complex are to be housed in temporary accommodation from next week. Thirty-seven families are to be put up in apartments near Priory Hall provided by the National Assets Management Agency (Nama) and five families are to be housed by a voluntary housing association.

Other residents remain in two Dublin hotels and in accommodation sourced by themselves.

READ MORE

The president of the High Court, Mr Justice Nicholas Kearns, was updated yesterday on the progress of the works being carried out, on foot of court orders, by developer Thomas McFeely, whose Coalport Building Company built the apartments in 2006. The judge had ordered those works to be completed by November 28th with the court to monitor progress weekly.

Yesterday marked the first monitoring hearing and Mr McFeely was in court. His counsel, Martin Hayden SC, sought a variation of a freezing order on his accounts to allow him living expenses. Mr Hayden asked for €2,000 weekly to meet mortgage and other payments but Mr Justice Kearns said, in the circumstances, he would allow €1,000.

John O’Donnell SC, for some residents, had earlier said the court could take it his clients were not consenting to any payments “of any sort” to Mr McFeely.

Fire safety inspector Donal Casey told the judge he was broadly satisfied with the fire safety works being carried out but had concerns about other matters at the complex not related to fire safety. There was a report indicating some mortar was soft and wall ties were inadequate, he said.

Mr Casey also said he was anxious to get a schedule of works covering the total period up to November 28th in an effort to ensure the works would be completed by that date.

Having visited the site twice in recent days, Mr Casey said he was satisfied it was not necessary to take down the entire external walls of the complex and work could be carried out on sections of that. Much of the external walls had been removed and he observed cavity barriers incorrectly fixed and in the wrong locations. The works carried out to date were broadly consistent with the works agreed.

Conleth Bradley SC, for the council, said the case was about reducing the fire safety risk to an acceptable level and the other matters raised were not before the court.

Mr O’Donnell asked that they be provided with certification of the works, a schedule of proposed works and information concerning insurance of the complex. He understood a building control investigation report would be available in two weeks and his clients wanted a copy of that to see “what else is wrong” with the complex.

Vincent Martin, for other residents, said three mortgage lenders had agreed to a three-month moratorium on mortgage payments for some residents. His clients also had concern about the adequacy of Mr McFeely’s funds and wanted to see his statement of affairs.

Mr Justice Kearns said he would not, at this stage, direct disclosure of the statement of affairs.

Mary Carolan

Mary Carolan

Mary Carolan is the Legal Affairs Correspondent of the Irish Times